I revisit the electrification story about once a year and the situation never seems to change--it is taking longer than expected, costing more than expected and the duration and total costs are still unknown; as is the money source. Here are some snippets from the DJ article:
Following the Friday announcement of additional cost overruns for Caltrain’s electrification modernization project, its board has authorized spending increases to ensure its completion, despite concerns over where funding will materialize. Caltrain’s electrification project faces $462 million in additional costs following its settlement agreement with contractor Balfour Beatty Infrastructure, higher than its initial June estimate of $333 million. COVID-19 related delays, utility issues and real estate have also played a role in increasing costs, Caltrain staff said.
Board Member Steve Heminger supported the additional funding for the project. However, he cautioned the board to prepare for the worst when it comes to a funding strategy. Heminger noted only slightly more than half of the extra costs are known and covered through federal grants and Measure RR funds, with the rest still to be found. It has received around $52.4 million from the federal government... Credit financing will cover another $150 million, with Measure RR capital reserve funding accounting for $60 million.
That last bit, using Measure RR funds, is controversial because the alternative is "relying on member agency funding". "$100 million here, $100 million there, pretty soon you are talking about real money" to paraphrase C. Everett Dirksen. You can guess what that means. At least the catenary wires have arrived in B'game as seen here near B'way. And the bulk of the work on this is above ground. Keep that in mind at the El Camino Real project gets discussed.
Your government tax dollars at work. Expect more cost over runs now that the Biden’s infrastructure bill boondoggle is law.
It’s all free, too!😏
Posted by: Chocolate, chocolate chip! | December 09, 2021 at 12:33 PM
At least there are wires are finally strung on the poles, now. I was starting to wonder if we were just going to have the pole part!
Posted by: Jennifer Pfaff | December 09, 2021 at 04:28 PM
Nothing like investing hundreds of millions and/or billions of dollars in 1830's technology!
Posted by: Paloma Ave | December 09, 2021 at 05:51 PM
When has a public works project ever come in on time and under budget?
Posted by: Christopher Cooke | December 10, 2021 at 04:27 PM
And HSR keeps chugging along…
“With no end in sight to the pandemic-induced downturn in public transportation ridership, many Bay Area transit agencies are warily eyeing their operating budgets, which have been kept afloat by billions in federal relief money during the public health crisis.
Riders are not returning in force and without their ticketing revenue, transit operators are burning through federal funds with hundreds of millions in budget shortfalls on the horizon. That means transit agencies are looking for new cash and voters may be asked to foot the bill in the coming years if they want to avoid service cuts.
“Everybody is asking how long the runway might be for the federal money provided and nobody knows the answer to that,” said Seamus Murphy, the executive director of Water Emergency Transportation Authority, which runs the San Francisco Bay Ferry. “Our fiscal cliff is imminent. … It’s all dependent on how ridership returns.”
Nearly two years after public health lockdowns collapsed public transportation ridership overnight, transit operators around the country are acknowledging that many riders will not be back for the foreseeable future. Remote work has become a permanent lifestyle for much of the workforce and rising COVID-19 case numbers and the omicron variant continue to push away would-be passengers from public transportation.”
Mercury News 12/20/2021
Posted by: Peter Garrison | December 20, 2021 at 07:16 AM
Even better: Headline for DJ notes “…Burlingame slated for thousands of new homes” to be built as a “transit oriented community…”
Posted by: Peter Garrison | December 20, 2021 at 11:47 AM
Geez. I thought the "billions and billions" from High-cost rail would cover the short little hop from SJ to SF.....guess I was wrong
California’s two U.S. senators are calling for legislative funding to complete Caltrain’s electrification service project, which recently completed a key construction milestone to ensure an electric train system runs from San Francisco to San Jose.
California Sens. Dianne Feinstein and Alex Padilla Friday sent a letter to the Department of Transportation asking for federal funding to finish the Caltrain Peninsula Corridor Electrification Project. The pair called for dedicated funding from the recently passed $550 billion Bipartisan Infrastructure Law to help Caltrain address a $410 million shortfall due to cost increases.
https://www.smdailyjournal.com/news/local/senators-seek-funding-for-caltrain-electrification/article_50589dfc-80bc-11ec-a852-e757d1332713.html
Posted by: Joe | January 30, 2022 at 12:27 PM
The "gantry" approaches. From the city e-newsletter today:
PARALLELING STATION CONSTRUCTION NOTICE
Caltrain is beginning construction of the first main gantry structure at the Paralleling Station facility currently under construction in Burlingame. Gantries are H-frame steel structures that support wires perpendicular to the tracks. These wires connect to the overhead contact system and provide power to the trains. The main gantry will be housed within the footprint of the facility near the transformers. The other gantry will be located on the opposite side of the tracks from the facility. A sample photo of a main gantry is located on the reverse side.
The Paralleling Station is an unmanned facility that will regulate electrical power to the electric trains. In addition to the gantries, the Paralleling Station will consist of:
• One transformer- The transformer will take in and convert power to ensure it is consistently sent out throughout the system.
• Control House - Located within the facility footprint, housing the controls for the system.
CONSTRUCTION ACTIVITIES
In addition to delivery of and installation of gantries via a crane, construction activities during this time will include excavation, laying of a concrete pad, control house construction, transformer delivery. Crews will utilize excavation equipment, and dump trucks for removal and delivery of materials.
A majority of the work will take place during the weekday between 6 a.m. and 3 p.m. There may be night and weekend work required when work is being completed within the railroad track envelope.
Posted by: Joe | March 31, 2022 at 04:04 PM
The DJ article about this weekend's closure from Hillsdale to Palo Alto also gave a progress report:
Caltrain is suspending its service between Hillsdale and Palo Alto stations on the weekends of July 15-16 and 22-23 to accommodate Caltrain electrification construction and testing. Construction crews will continue to erect poles and hang wires for the overhead catenary system.
These will be the 15th and 16th of approximately 30 weekends in 2023 in which service will be adjusted to accommodate construction and testing for electrified service, which is expected to launch passenger service in fall 2024. Thus far, construction crews have installed 59 poles this year along with over 431,000 feet of wire.
Posted by: Joe | July 13, 2023 at 01:24 PM
4,200 people toured the demonstration e-train car down in San Jose:
Nevertheless, the arrival of rider-ready electric trains in fall 2024 is generating excitement among Caltrain riders eager to board the sleek, quieter and cleaner trains. Last weekend, roughly 4,200 people queued up in the parking lot at San Jose’s Diridon Station to tour new trains parked on a siding.
Once the trains and power system are deemed to be in proper working condition, he said, each train set needs to be run for at least 1,000 miles before it can carry passengers.
Electrifying Caltrain will cost an estimated $2.4 billion, with funds coming from state, federal and local sources.
So far, about 90% of the overhead wire — more than 400,000 feet — has been hung during shutdowns and 59 poles erected. The longest uninterrupted stretch completed is between Palo Alto and San Jose.
Electrifying Caltrain will cost an estimated $2.4 billion, with funds coming from state, federal and local sources.
So far, about 90% of the overhead wire — more than 400,000 feet — has been hung during shutdowns and 59 poles erected. The longest uninterrupted stretch completed is between Palo Alto and San Jose.
Posted by: Joe | August 04, 2023 at 01:29 PM
Here's an e-update:
The successful completion of several live runs, short circuit testing and the arrival of new train sets are keeping the Caltrain electrification project on pace, but unanticipated challenges, including increased instances of theft and vandalism, raise concerns about potential cost implications.
Passengers can start expecting the new electrified service in September, which will include at least 20% more stops at each station. The Caltrain electrification project broke ground around 2017, and it marks the first time in at least three decades a diesel railway has converted to an electrified system in the country.
https://www.smdailyjournal.com/news/local/theft-plagues-caltrain-electrification-updates/article_89f83bfa-b4ed-11ee-8a85-fb661d96adc3.html
Posted by: Joe | January 25, 2024 at 02:42 PM
The rumor about major theft of copper wire on the electrified Caltrain line appears to be true per yesterday's DJ article. Way at the bottom we read:
The seven-year effort hasn’t seen ballooning budgetary needs as of late, and it’s also reported few injuries. But it’s most recently struggled to curb incidents of tampering with or stealing impedance bond cables, which ensure the higher voltage and lower voltage currents do not interfere with one another. The cables, which have cost in total $2.5 million, have continued posing risks throughout the project, both from a financial standpoint and from a safety perspective. There have been over 100 incidents of vandalism and thefts since the start of construction, the majority of which involve the cables.
-----------------------
That is a little unclear, but I'm going to say the $2.5 million is for replacing stolen cable--it's too low for the initial cost. This is likely to be an on-going problem---just like stolen catalytic converters. It's easy to imagine days and days of no service whenever the scrappers do their thing.
Posted by: Joe | May 15, 2024 at 12:25 PM
Electric Caltrain is almost here. The first trial runs happened last week and into this week. Unfortunately, we also had our first E-train fatality in Menlo Park which only the Post reported after noting Caltrain will no longer report fatalities on the tracks (??).
There's lots of chatter about the new trains being quieter, but the bulk of the train noise are the required horns and the bells at the crossing gates.
And on a fun note:
Caltrain to auction off used diesel locomotives after full electrification begins
20 old trains, which were retired after the transit agency went fully electric, will be up for bid in late September
Caltrain has opened an online store with the hope of auctioning off 20 retired diesel locomotives that can be repurposed as a brewery, store, community center or cozy home.
An opening bid for the auction, which is slated to start in late September or October, hasn’t been set yet, but agency officials are already thinking of creative ways to get the most out of the unusual offering.
“The Caltrain store is a great shopping experience for everyone, from Caltrain riders to Bay Area residents to rail fans across California,” said Caltrain Executive Director Michelle Bouchard in a statement. “I particularly recommend the F40 locomotives, which would be perfect for a creative planter box, a cozy bed-and-breakfast or a conversation piece for your mantel.”
That’s provided that your mantel is reinforced to support a 137-ton locomotive.
-------------------
LOL
Posted by: Joe | August 15, 2024 at 02:29 PM
Crikey!
The first several weekdays with a fully electric train fleet have already seen two power outages and major delays, both caused by instances of equipment vandalism and theft.
Caltrain celebrated its electrification launch on Saturday, Sept. 21, but just two days later, an hourlong outage led to even longer delays and cancellations after someone tampered with the overhead contact system at the San Mateo train station. The next day, the theft of impedance bond cables — which ensure the higher voltage and lower voltage currents do not interfere with one another — near the 22nd Street station caused another outage and subsequent delays. Disruptions continued on Wednesday as the agency worked to replace the equipment.
Bond cable thefts were an ongoing concern during the construction phase. More than 100 incidents of theft and vandalism were reported, the majority of which were related to the cables, typically stolen for their copper components.
Caltrain Chief Modernization Officer Prayana Shrestha has said during several Caltrain board meetings that redesigning the cable installation would be costly, though the financial burden incurred would still be lower than ongoing replacement and repair costs due to theft.
-------------------------------
The Law of Unintended Consequences will NOT be denied.
Posted by: Joe | September 26, 2024 at 01:00 PM
Here's another instance of economic reality mugging climate hopefulness:
Retired diesel-powered Caltrain fleet to be transferred to Peru to address transportation issues
Caltrain will be reimbursed over $6 million for the deal
After seven years of electrification work, Caltrain switched to all-electric trains on their 51-mile corridor between San Jose, San Francisco and Gilroy on Sept. 21. With the majority of their diesel fleet retired, Caltrain offered 19 diesel locomotives and 90 retired silver gallery cars for sale. The municipal government of Lima, Peru, agreed to pay $6 million for the fleet to support a line between Lima and the district of Lurigancho-Chosica.
Posted by: Joe | November 16, 2024 at 05:21 PM
Send our pollution somewhere else…
But we’re helping the environment.
Global warming and sea rise doesn’t occur south of the equator.
Posted by: Peter Garrison | November 18, 2024 at 08:09 AM